How to Track Labor Costs on Grant-Funded Utility Projects

Federal and state funding is helping utilities move forward with infrastructure projects that might otherwise compete for limited capital budgets. From substation improvements to distribution system upgrades, these investments create opportunities to improve reliability while reducing the financial burden on utilities and their customers.

In October 2026, the U.S. Department of Energy (DOE) announced approximately $967 million in additional funding through its Grid Resilience State and Tribal Formula Grant Program. The program provides funding to states, territories, and tribes, which can then award funds to eligible entities for qualifying grid resilience projects.

For utilities receiving grant funding, managing the project involves more than completing the approved work. They must also account for how funds are spent, including the employee labor charged to the project.

Labor documentation is particularly challenging when utility crews divide their time between grant-funded improvements and routine operations. Without a reliable way to allocate those hours, finance teams may struggle to support the costs reported against a grant.

What Labor Costs Can Utilities Charge to a Grant-Funded Project?

Eligible labor costs depend on the grant program, the approved project scope, and the terms of the award or subaward agreement. Federal funding does not automatically make every expense associated with a utility project reimbursable.

For federal awards subject to the Uniform Guidance, 2 CFR § 200.430 establishes standards for documenting employee compensation charged to an award.

The regulation requires salary and wage charges to be supported by records that accurately reflect the work performed. Those records must be part of the organization’s official records and supported by internal controls that provide reasonable assurance of accurate and allowable charges.

Utilities should establish which labor activities qualify under their award before work begins. A grid resilience project may include several types of field activity, but costs must still fall within the approved scope and applicable eligibility requirements.

Finance and project managers should also agree on how eligible work will be identified in the utility’s timekeeping and accounting systems.

Connecting Employee Hours to Grant-Funded Work Orders

Consider a utility that receives funding for distribution system improvements. Crews are assigned to replace aging infrastructure, but they continue handling routine maintenance and service calls throughout the project.

An employee might spend six hours working on the funded improvement project and two hours responding to an unrelated maintenance request.

Payroll needs to account for all eight hours. Grant reporting, however, needs to distinguish the six hours associated with the funded project from the two hours spent on routine operations.

If the timesheet records only the employee’s total hours, finance may have to reconstruct the allocation using work orders or supervisor notes.

Assigning employee time to specific work orders provides a more reliable record of how labor was used. Each work order can be associated with the appropriate project and accounting structure, allowing finance to separate eligible activities from other utility work.

Field employees should be able to select familiar work assignments rather than determine grant eligibility themselves. The utility’s established project and cost-code structure can then support the appropriate financial classification.

This approach is also useful when crews move between capital improvements and routine operations. Our article on capital versus O&M labor tracking explains how utilities can structure time and cost codes to support those distinctions.

Documenting Labor Used for Grant Cost Sharing

Some grant programs require recipients to contribute a portion of the total project cost. Depending on the program and award conditions, qualifying employee labor may be eligible to count toward that contribution.

DOE’s Grid Resilience State and Tribal Formula Grant Program allows certain cash and in-kind contributions, including qualifying staff time, to be used for cost matching.

Under 2 CFR § 200.306, cost-sharing contributions must be verifiable in the recipient’s or subrecipient’s records. They must also meet applicable allowability requirements and cannot generally be counted toward another federal award.

Employee wages used to satisfy cost-sharing requirements are subject to the same documentation standards as wages charged directly to federal awards.

A utility planning to use staff time as part of its contribution therefore needs records showing the work performed and the associated labor cost. The hours must be supported by appropriate compensation information and allocated to the qualifying activity.

Accurate project time tracking makes it easier to identify those contributions, but the utility must still confirm that the labor qualifies under its specific award.

Reviewing Labor Costs Before Grant Reporting

Timesheets should be reviewed while supervisors can still verify the work performed. An employee may have entered the correct hours but selected the wrong work order, or a supervisor may need to clarify whether an activity belongs within the funded project.

Finding these issues before the time reaches accounting reduces the effort involved in correcting project costs later.

A practical review process should establish several basic controls:

  • Project assignments: Confirm that employee hours are charged to the correct project and work order.
  • Actual hours: Verify that recorded time reflects the work performed, including hours spent on unrelated assignments.
  • Approvals: Have the appropriate supervisor review entries before they are processed.
  • Cost calculations: Reconcile approved hours with applicable pay rates and payroll records.
  • Supporting documentation: Retain records that substantiate the labor charged to the funded project.

These controls also help utilities prepare for financial reviews after the project is complete.

Federal award recordkeeping requirements generally call for records to be retained for three years from the submission of the final financial report, although exceptions and extensions apply. The applicable requirements are outlined in 2 CFR § 200.334.

Utilities should review their award agreements and any applicable state requirements when establishing their documentation and retention procedures.

How Utility Time Tracking Software Supports Grant Documentation

Collecting the required information shouldn’t create unnecessary work for field crews.

Employees need a straightforward way to record hours against assigned projects and work orders. Supervisors need to verify those entries, while finance needs the approved information available for project accounting and grant reporting.

Journyx time tracking for utilities supports detailed labor allocation through configurable timesheets, validation rules, and approval workflows.

Utilities can configure project and work-order selections to reflect their operational structure. Validation rules help identify missing or incorrect information before submission, while approval workflows allow supervisors to review entries according to the organization’s procedures.

Journyx also provides integrations with ERP and accounting systems, helping utilities transfer approved time information into the systems responsible for financial processing.

For organizations managing multiple infrastructure projects, this provides a consistent method for collecting labor information without relying on separate spreadsheets for each funding source.

Journyx does not determine whether an expense qualifies for grant reimbursement or cost sharing. Those decisions remain subject to the applicable award requirements and the utility’s accounting procedures. Its role is to help organizations capture accurate labor records and maintain the information needed to support those decisions.

Prepare Labor Records Before Project Work Begins

Grant reporting becomes more difficult when labor documentation is addressed only after expenses have accumulated.

Before beginning a funded project, utilities should confirm how eligible work will be identified in their timekeeping system and how supervisors will review employee hours. Finance should also establish how those records will connect to the approved project budget and grant reporting requirements.

A consistent process gives utilities more reliable labor cost information throughout the project and reduces the amount of documentation that must be reconstructed later.

Know where every labor hour goes. And have the record to prove it.

See how Journyx helps utilities capture and validate project labor.

This article provides general information about grant-related labor documentation. Eligibility, cost-sharing requirements, and reporting obligations vary by program and award. Utilities should consult their award agreements and applicable grant administrators before determining whether specific labor costs qualify.